Juru-Sungai Dua Traffic Dispersal Project Reaches Over 54% Completion

Penang:Package 1 of the Juru-Sungai Dua Traffic Dispersal Project (PTJSD) in Penang has achieved 54.61 percent physical progress as of November 8, marking significant advancement in the strategic infrastructure initiative.

According to BERNAMA News Agency, PLUS Malaysia Berhad (PLUS) announced that Package 1 includes improvement works to the access ramps at the East-West Interchange Roundabout and the construction of a new bridge along Jalan Tun Hussein Onn. These developments aim to increase road capacity and improve traffic flow in the area.

Additionally, the planning for subsequent packages is underway, with Packages 2 to 5 currently in the final tendering stage. Packages 2 and 5 involve construction along sections between Juru Toll Plaza and Juru Lay-by, as well as between Samagagah Lay-by and Sungai Dua Toll Plaza. Meanwhile, Packages 3 and 4 involve the construction of elevated sections and interchanges between Juru Lay-by and Samagagah Lay-by.

Overall, the PTJSD is a RM3 billion infrastructure project spanning 17.4 kilometers, connecting Juru Toll Plaza and Sungai Dua Toll Plaza. Once completed, the project is expected to enhance highway capacity, improve traffic flow, and deliver long-term benefits to highway users and the surrounding communities.